How long does an office fit-out take?

Typical UK office fit-out timescales from design to handover, what causes delays and how to keep a project on programme.

Updated 18 September 2026. Figures are indicative and exclude VAT.

Metal stud partitions with acoustic insulation being built in an officeIllustrative image

Quick answer

Most UK office fit-outs of 2,000 to 10,000 sq ft take 6 to 12 weeks on site. With design, pricing and landlord approval beforehand, the whole process from first survey to moving in is usually 3 to 5 months.

Typical stages

Survey and brief takes about a week. Layouts and design take 2 to 4 weeks. Pricing and landlord licence take 2 to 6 weeks. Construction takes 6 to 12 weeks. Snagging and handover take about a week.

What causes delays?

Late decisions on layout or finishes, waiting for landlord consent, long-lead items such as glass partitions, bespoke joinery and air conditioning plant, and discovering problems above ceilings or below floors.

How to keep to programme

Fix the layout early, order long-lead items as soon as the design is signed off, and start the landlord licence process in parallel with design. A survey that opens up ceilings and floors reduces surprises.

More guides

Next step

Send us the floor plan. We will tell you what it really costs.

A free site walk anywhere in the UK, an honest read on the building and a budget range, with no follow-up calls you did not ask for.

Book a free site survey
Or speak to the team0800 088 6248Mon to Fri, 8am to 6pm
CallGet a price